City of Hart, Michigan
NOTICE OF PUBLIC HEARING
Michigan Community Development Block Grant (CDBG) Program
Project No. MSC 209123-CDI, Downtown Streetscape
The City of Hart will receive public comments regarding the proposed Downtown Streetscape project on Tuesday, February 9, 2010, 7:30 PM at City Hall, 407 State Street, Hart, Michigan. Documents including the Community Development Plan, Project Description, Project [...]
City of Hart, Michigan
MEMORANDUM
To: MAYOR CLANCY AERTS & CITY COUNCIL
From: STAN RICKARD, City Manager
Date: February 8, 2010
RE: WEST HART SUBSTATION
Late on February 5, 2010, GRP Engineering sent slightly revised engineering and construction costs for the West Hart Substation as follows: $541,662 which includes an additional $68,400 for electric distribution improvements in the vicinity of Plum [...]
City of Hart, Michigan
MEMORANDUM
To: MAYOR CLANCY AERT & CITY COUNCIL
From: STAN RICKARD, City Manager
Date: February 5, 2010
RE: WEST HART SUBSTATION
At the January 26, 2010 City Council meeting, we discussed several prospective capital improvement projects in light of a recent announcement from the Michigan Economic Development Corporation about another round of Community Development Block Grant funding opportunities. [...]
Council will consider a grant application for Downtown Gateway Streetscape improvements. Project proposed for NE corner of State & Main. Join us at City Hall, 407 State Street, Hart, MI
City of Hart, Michigan
MEMORANDUM
To: Mayor Clancy Aerts & City Council
From: STAN RICKARD, City Manager
Date: February 5, 2010
RE: Downtown Streetscape – Full Application for CDBG Funding
On December 22, 2009 City Council approved Resolution 09-78 authorizing a full application for Community Development Block Grant funds for the State & Main streetscape project in the amount of $436,090. The local [...]
City of Hart, Michigan
MEMORANDUM
To: MAYOR Clancy Aerts & City Council
From: STAN RICKARD, City Manager
Date: February 5, 2010
RE: CITY MANAGER’S REPORT
Streetscape Project – Corner Lot at State & Main (3 State Street)
John Byl, Attorney, Warner Norcross in Grand Rapids is reviewing the environmental status of this property, the proposed site for the downtown streetscape project.
TIFA agreed [...]
City Hall is open and observing President’s Day.
Watch for the new images from our Historic District coming soon.