Welcome to Hart Beat

City Manager's Blog, important links, RSS News Feeds & Tweets.

Public Hearing 2/9

City of Hart, Michigan

 NOTICE OF PUBLIC HEARING

Michigan Community Development Block Grant (CDBG) Program

Project No. MSC 209123-CDI, Downtown Streetscape

 The City of Hart will receive public comments regarding the proposed Downtown Streetscape project on Tuesday, February 9, 2010, 7:30 PM at City Hall, 407 State Street, Hart, Michigan.  Documents including the Community Development Plan, Project Description, Project [...]

Revised costs-Substation 2/8

City of Hart, Michigan

MEMORANDUM

To:           MAYOR CLANCY AERTS & CITY COUNCIL

From:     STAN RICKARD, City Manager

Date:      February 8, 2010

RE:           WEST HART SUBSTATION

Late on February 5, 2010, GRP Engineering sent slightly revised engineering and construction costs for the West Hart Substation as follows:  $541,662 which includes an additional $68,400 for electric distribution improvements in the vicinity of Plum [...]

PROPOSED WEST HART SUBSTATION

City of Hart, Michigan

MEMORANDUM

To:          MAYOR CLANCY AERT & CITY COUNCIL

From:     STAN RICKARD, City Manager

Date:      February 5, 2010

RE:           WEST HART SUBSTATION

At the January 26, 2010 City Council meeting, we discussed several prospective capital improvement projects in light of a recent announcement from the Michigan Economic Development Corporation about another round of Community Development Block Grant funding opportunities.  [...]

City Council meeting - Tuesday, February 9, 2010, 7:30 PM

Council will consider a grant application for Downtown Gateway Streetscape improvements. Project proposed for NE corner of State & Main. Join us at City Hall, 407 State Street, Hart, MI

Gateway Streetscape

 

City of Hart, Michigan

MEMORANDUM

To:           Mayor Clancy Aerts & City Council 

From:     STAN RICKARD, City Manager

Date:     February 5, 2010

RE:           Downtown Streetscape – Full Application for CDBG Funding

On December 22, 2009 City Council approved Resolution 09-78 authorizing a full application for Community Development Block Grant funds for the State & Main streetscape project in the amount of $436,090.  The local [...]

Feb 5, 2010 Report

City of Hart, Michigan

MEMORANDUM

To:           MAYOR Clancy Aerts & City Council

From:     STAN RICKARD, City Manager

Date:      February 5, 2010

RE:           CITY MANAGER’S REPORT

Streetscape Project – Corner Lot at State & Main (3 State Street)

John Byl, Attorney, Warner Norcross in Grand Rapids is reviewing the environmental status of this property, the proposed site for the downtown streetscape project.
TIFA agreed [...]

Celebrating President’s Day

City Hall is open and observing President’s Day.

Historic Slide Show

Watch for the new images from our Historic District coming soon.